What had been an hour-plus work session update on Capital Improvement Projects (CIPs) by County Project Manager Jeff Hayes took an unexpected turn about an hour and a quarter into that work session at the conclusion of Hayes PowerPoint presentation. I say “unexpected” because the only open session agenda cover sheet item was Hayes’ CIP report. However, the board elected to take what was labeled “Closed Session” discussion of “Personnel re: Economic Development Authority” into open session discussion.
What followed was County Administrator Ed Daley’s presentation on organizational opportunities presented by the pending October 1st loss of the second and final member of the two-person EDA staff. As previously reported, following Administrative Assistant Gretchen Henderson’s August 27 departure to the Northern Shenandoah Valley Regional Commission, Executive Director Doug Parsons announced his resignation, effective October 1, to take the EDA executive director’s job in Fauquier County.

Warren County Administrator Ed Daley explains the operational dynamics of realigning the EDA staff within the County’s administrative structure inside the WCGC. Royal Examiner Photos by Roger Bianchini
And what Daley presented to the board in open session echoed what EDA Board Chairman Jeff Browne told Royal Examiner in the wake of the pending loss of the entire EDA staff – this can be an opportunity, rather than a derailing of the EDA’s recovery from the multi-million-dollar financial scandal uncovered in 2018-19 under previous executive and board leadership. And while Browne focused on replacement personnel selection as the opportunity, Daley used that as a jumping-off point to explore previous supervisors discussion dating to early 2020 about an organizational realignment of the EDA. The County has already taken on the role of Financial Agent of the EDA. Continuing the broached realignment would bring the EDA staff into the Warren County Government Center, functioning more like a County Department. That option was first considered by some supervisors in the wake of the Town of Front Royal’s decision to operationally withdraw from the half-century-plus old joint EDA, in favor of creating its own unilateral Front Royal EDA (FREDA).

In Dec. 2019 file photo, then-Mayor Gene Tewalt at an EDA Board meeting. Tewalt urged Town Council to accept EDA-offered negotiations to determine exactly what the Town’s losses in the EDA financial scandal were – but council wasn’t listening. Will they now? Then EDA Board Chairman Ed Daley is at far left, flanked by Greg Harold, Doug Parsons, Jeff Browne, standing, a partially obscured Gray Blanton, and Jorie Martin. Now Supervisors Chair Cheryl Cullers is seated behind Mayor Tewalt.
That decision was driven by the Town Council’s decision, against the advice of then-Mayor Gene Tewalt, to civilly sue the old EDA for a larger portion of the allegedly embezzled and misdirected EDA assets related to County and Town business dealing handled by the EDA. Rather than costly and divisive litigation, Mayor Tewalt urged council to accept the new EDA leadership’s offer to have staffs simply sit down and follow the money to determine who was owed what. However, a council majority wasn’t listening to its then mayor. Consequently, the Town and EDA are currently engaged in dueling civil litigations.
And while Daley’s presentation began as a logistical exploration of processes of incorporating the EDA into the county governmental apparatus, it took a turn when one supervisor posed a legal question. “I’m going to call the elephant out in the room,” North River Supervisor Delores Oates said in pointing out that the existing EDA was jointly founded by the county and town governments over a half-century ago, and legally remains a Town-County EDA. So, can the County legally bring the EDA into its sole administrative oversight, she wondered.
“If I were sitting where you sit, I would invite the town council to participate in a staffed economic development department that works for the EDA but can also work for us in the County and the Town on economic development projects,” the county administrator replied. And as Daley pointed out, neither EDA currently has a staff, though at least one, the old EDA, has an exceptionally competent and proactive re-tooled board of directors.
“And I think that would be the best tactical advantage for the community, is if we would actually collaborate and not create independent organizations. Because otherwise we’re spending twice the money to do the same job,” Oates said in response to Daley’s suggestion.

Fork District Supervisor Archie Fox wondered how close to day-to-day EDA operations the county supervisors really wanted or needed to be. Below, North River Supervisor Delores Oates called ‘the elephant out in the room’ – the fact that legally the existing, co-founded EDA remains the ‘FR-WC EDA’. So, can the Board incorporate it into the county governmental apparatus were that path chosen?

The first face-to-face discussion of this latter option of reestablishing a jointly functioning Town-County EDA will apparently take place this Thursday, at the first Town-County Liaison Committee meeting since the Town Council decided to cut those quarterly meetings off in the wake of initiating the now dueling Town-EDA/County civil litigations. Daley noted that Liaison Committee opportunity was presented by the inclusion on Thursday’s Liaison agenda of a Town presentation on the status of development of its unilateral Town EDA.
Members of both council and the board of supervisors have recently suggested an altered, more collaborative Town-County path forward from the divisive and litigious one launched by council during the tenure of Interim Town Manager Matt Tederick. So, it will be interesting to see how Thursday’s Liaison Committee discussion develops with a new town manager involved; and how the full council will react to the idea of realigning into a jointly functioning EDA apparatus, possibly including collaboration in selecting the new FR-WC EDA staff were a speedy, positive reaction achieved.
The EDA discussion begins at the 1-hour-16-minute-30-second mark of the linked county video; Oates calls out the “elephant in the room” at the 1-hour-44-minute-45-second mark. The Capital Improvement Project PowerPoint and Q&A takes up the first hour-and-15-minutes of the video. And between the CIP and EDA portions of the work session, Board Chair Cullers gave an update on news of the birth of her newest grandchild Tuesday evening. – Welcome to the world on September 14, 2021, Ella Louise.
About those CIP projects
Prior to that turn toward the EDA and Town-County relations regarding cost-effective cooperation versus costly, counterproductive competition in future economic development initiatives, there were some interesting turns on the CIP front. Those included discussion of downtown Front Royal parking issues and the County’s ability to impact those issue with owned property in the Historic Downtown Business District vicinity. Also, under board scrutiny was the cost and effectiveness of air purification devices under consideration for other County facilities after being installed at the Warren County Courthouse to allow more normal judicial proceedings to be reinitiated during the COVID-19 Coronavirus pandemic. Discussion of the potential effectiveness against, not only the COVID-19 Coronavirus but other virally spread illnesses was broached in considering the purchase of as many as 60 of the machines at a cost of $2100 per unit.

County Project Manager Jeff Hayes had the floor with a power point review of Capital Improvement Projects for the first hour-and-15-minutes of work session.
See Hayes’ CIP power point on renovations to the Commonwealth Attorney’s Office; the Parks & Rec Department Splash Pad Pavilion; Rivermont Volunteer Fire Company 2 renovations; Shenandoah Farms Company 6 renovations; the Morgan’s Ford Boat Landing project; and Juvenile and Domestic Court renovations and related parking issue, including the observation that you “don’t build a court facility over or under a parking deck – BOOM!” (due to domestic terrorist concerns).