I-66 Outside the Beltway Project: Lane closures and traffic changes – Week of March 8, 2020

Published

on

Transform 66 Outside the Beltway Project construction continues throughout the corridor during daytime and overnight hours as weather conditions allow.

Significant upcoming traffic impacts include:

• I-66 narrowed to one lane in each direction on Saturday, March 7, in western Fairfax County for demolition of the Bull Run Drive bridge over I-66 East. Both directions of traffic will use I-66 East for about one mile. Details

• Utility work near Cedar Lane on the nights of March 8, 13, and 14 will narrow I-66 to one lane in each direction between 9 p.m. and 5 a.m., with occasional 20-minute stoppages. Details

• Overnight ramp closures at I-66 West to Route 28 North (Sunday, March 8); I-66 East to Route 123 (Monday, March 9); I-66 East to Route 28 North (Wednesday, March 11, through Friday, March 13); and Route 50 West to I-66 West (Thursday, March 12). Details

• Bridge pier construction will require overnight closures of two lanes on I-495 North and of three lanes on I-495 South near I-66 from Monday, March 9 through Friday, March 13.

Current activities include:

• Bridge demolition at Bull Run Drive and Fairfax County Parkway (Route 286)

• Constructing bridge foundations at Route 29, Route 28, Waples Mill Road, Jermantown Road, Route 123, Vaden Drive, and I-495

• Small charge dynamite operations along Route 28 and I-66 East and West near Route 28

• Bridge deck work for new collector-distributor road over Route 234 Business (Sudley Road), expanded bridge over Compton Road, new Route 28 bridges over I-66, and new Poplar Tree Road bridge over Route 28

• Relocating water lines at Jermantown Road, Stringfellow Road, and Gallows Road

• Constructing new utility duct bank and relocating underground utilities along I-66 East

• Constructing retaining walls along I-66 and Route 28

• Corridor-wide roadway maintenance as needed

 

The Transform 66 Outside the Beltway project will add express lanes stretching 22.5 miles from the Capital Beltway to Route 29 in Gainesville, rebuild major interchanges along the I-66 corridor, create thousands of new park and ride spaces, and expand trail options for cyclists and pedestrians. Learn more at Transform66.org.

 

Upcoming Lane Closures and Traffic Changes
The following planned lane closures are expected to have significant traffic impacts. All work is subject to change based on weather and schedule. Find the latest information on travel conditions and work zones by visiting 511virginia.org or downloading the Virginia511 app.

ROUTE 29 / GAINESVILLE
No significant traffic impacts scheduled.

ROUTE 234 BUSINESS (SUDLEY ROAD) / MANASSAS
I-66 West between Compton Road and Route 234 Business (Sudley Road)
Tuesday, Mar. 10: 9 p.m. to 6 a.m.
Three lanes will be closed for overhead gantry removal. Drivers should expect periodic 20-minute stoppages between midnight and 4 a.m.

I-66 East and West at Bull Run Drive
Saturday, Mar. 14: 9 p.m. to 9 a.m.
I-66 will be reduced to a single lane in each direction under Bull Run Drive. Two-way traffic will run on I-66 West during this period.

ROUTE 28 (SULLY ROAD) / CENTREVILLE
I-66 East and West between Route 29 Centreville and Stringfellow Road
Route 28 North and South between Route 29 and Braddock Road
Braddock Road at Route 28
Tuesday, Mar. 10, through Friday, Mar. 13: 11 a.m. to noon
Temporary 15-minute stoppages of traffic on I-66 East and West, Route 28 North and South, and on Braddock Road near Route 28 for blasting operations.

I-66 West between Stringfellow Road and Route 28
Ramp from I-66 West to Route 28 North
Sunday, Mar. 8: 9 p.m. to 5 a.m.
Two right lanes will be closed for overhead bridge work. The ramp from I-66 West to Route 28 North will also be closed between midnight and 4 a.m. Traffic will be detoured to Route 28 South, follow signs to Route 29 North, then stay to the right and follow signs to Route 28 North.

I-66 West between Fairfax County Parkway (Route 286) and Route 28
Monday, Mar. 9: 9 p.m. to 5 a.m.
Three left lanes will be closed for overhead bridge work.

Route 28 North between E.C. Lawrence Park athletic fields and Westfileds Boulevard
Tuesday, Mar. 10: 9 p.m. to 5 a.m.
Two left lanes will be closed for overhead bridge work.

I-66 East from Route 29 Centreville to Route 28
Tuesday, Mar. 10: 9 p.m. to 5 a.m.
Two left lanes will be closed for overhead bridge work.

I-66 East from Compton Road to Route 28
Ramp from I-66 East to Route 28 North
Wednesday, Mar. 11, and Thursday, Mar. 12: 9 p.m. to 5 a.m.
Friday, Mar. 13: 9 p.m. to 9 a.m.
Three left lanes will be closed for overhead bridge work at Route 28. The ramp from I-66 East to Route 28 North will also be closed between midnight and 4 a.m. Drivers will be detoured farther east to Fairfax County Parkway (Route 286) North, stay to the right for I-66 West, then follow signs to Route 28 North.

Route 28 South between Westfileds Boulevard and E.C. Lawrence Park athletic fields
Thursday, Mar. 12: 9 p.m. to 5 a.m.
Friday, Mar. 13: 10 p.m. to 8 a.m.
Two left lanes will be closed for overhead bridge work.

ROUTE 286 (FAIRFAX COUNTY PARKWAY) / FAIR LAKES
Stringfellow Road between Fair Lakes Boulevard and Village Square Drive
Monday, Mar. 9, through Friday, Mar. 13: 9 p.m. to 3 p.m.
Friday, Mar. 13, from 9 p.m. until 3 p.m. Monday, Mar. 16
The right lane of southbound Stringfellow Road will be closed for underground utility relocation. The lane will be reopened weekdays between 3 p.m. and 9 p.m. to accommodate the evening rush.

Route 286 (Fairfax County Parkway) South from Fair Lakes Parkway to I-66
Route 286 (Fairfax County Parkway) North from Lee Highway (Route 29) to I-66
Monday, Mar. 9, through Thursday, Mar. 12: 9 p.m. to 5 a.m.
Friday, Mar. 13: 10 p.m. to 8 a.m.
Two lanes will be closed for overhead bridge demolition of I-66 bridges over Route 286. Drivers should expect occasional 20-minute stoppages.

ROUTE 50 / FAIRFAX
I-66 East between Monument Drive and Route 50
Monday, Mar. 9: 9 p.m. to 5 a.m.
Two left lanes will be closed for crane mobilization.

Ramp from Route 50 West to I-66 West
Thursday night, Mar. 12: Midnight to 4 a.m.
The ramp will be closed for utility work. Traffic will be detoured farther west to Route 608 (West Ox Road) South, stay to the right for Route 50 East, then follow signs to I-66 West.

ROUTE 123 (CHAIN BRIDGE ROAD) / OAKTON – CITY OF FAIRFAX
I-66 East at Route 123 (Chain Bridge Road)
Ramp from I-66 East to Route 123 (Chain Bridge Road) North and South
Monday, Mar. 9: 9 p.m. to 5 a.m.
One lane will be closed on I-66 East for overhead sign removal. The ramp from I-66 East to northbound and southbound Route 123 will also be closed. Traffic will be detoured farther east to Route 243 (Nutley Street) North, stay to the right for I-66 West, then follow signs to Route 123 North and South.

I-66 West from Blake to Route 123 (Chain Bridge Road)
I-66 East from Route 50 to Route 123 (Chain Bridge Road)
Tuesday, Mar. 10, and Thursday, Mar. 12: 9 p.m. to 5 a.m.
Friday, Mar. 13: 9 p.m. to 9 a.m.
Three left lanes will be closed on westbound I-66, and two left lanes closed on eastbound I-66 for equipment mobilization and bridge pier excavation. Drivers should expect periodic 20-minute stoppages between midnight and 4 a.m.

ROUTE 243 (NUTLEY STREET) / VIENNA
I-66 West from I-495 to Cedar Lane
I-66 East from Route 123 to Cedar Lane
Sunday, Mar. 8: 9 p.m. to 5 a.m.
Friday, Mar. 13, and Saturday, Mar. 14: 9 p.m. to 9 a.m.
Three left lanes will be closed for relocation of overhead Verizon communication line. Drivers should expect occasional 20-minute stoppages in both directions between midnight and 4 a.m.

I-495 (CAPITAL BELTWAY) / DUNN LORING
I-495 North from Route 50 to I-66
Monday, Mar. 9, through Thursday, Mar. 12: 9 p.m. to 5 a.m.
Friday, Mar. 13: 10 p.m. to 8 a.m.
Two left lanes will be closed for bridge pier excavation.

I-495 South from Route 7 to I-66
Monday, Mar. 9, through Thursday, Mar. 12: 9 p.m. to 5 a.m.
Friday, Mar. 13, and Saturday, Mar. 14: 10 p.m. to 8 a.m.
Three left lanes will be closed for bridge pier excavation. Drivers should expect occasional 20-minute stoppages.

I-66 West from I-495 to Cedar Lane
I-66 East from Route 123 to Cedar Lane
Sunday, Mar. 8: 9 p.m. to 5 a.m.
Friday, Mar. 13, and Saturday, Mar. 14: 9 p.m. to 9 a.m.
Three left lanes will be closed for relocation of overhead Verizon communication line. Drivers should expect occasional 20-minute stoppages in both directions between midnight and 4 a.m.

Commuter Alternatives
VDOT and the project team have invested in a broad range of programs to help commuters and others stay mobile and safe during construction. Learn more about carpool, vanpool, telework, and commuter bus alternatives.

Front Royal, VA
61°
Cloudy
7:22 am6:34 pm EDT
Feels like: 61°F
Wind: 2mph NNW
Humidity: 97%
Pressure: 30.09"Hg
UV index: 0
FriSatSun
84°F / 48°F
54°F / 32°F
61°F / 36°F
National News5 hours ago

Trump: Execution of Fort Hood Shooter Will Not Be Livestreamed

Community Events5 hours ago

Harmony Hollow Holler Music Festival Brings Appalachian Music to Front Royal October 17

Local News7 hours ago

Winsome Earle-Sears Warns of Consequences of Virginia’s Proposed Constitutional Amendments

State News8 hours ago

Federal Emergency Order Aims to Prevent Power Outages Across Mid-Atlantic, Including Virginia

Crime/Court9 hours ago

Warren County Grand Jury Returns 17 Indictments Against 10 Individuals in October Session

Meet the Candidates11 hours ago

Text Amendment for Aging in Place Community Succeeds at County Planning Commission Meeting

State News12 hours ago

Virginia Lawmakers, Spanberger Grapple With Loss of Federal Healthcare Funds for Trans Youth 

State News12 hours ago

Virginia Sees Gains in Kindergarten Readiness, But Gaps Persist for Underserved Students

Paws & Claws14 hours ago

One Health: Why Animal Health Is Also Your Health

Interesting Things to Know15 hours ago

The Real Winnie-The-Pooh Was a Girl from Ontario

Crime/Court1 day ago

Defense Counsel and Special Prosecutor Reach Plea Agreement on Carter DUI Cases

Obituaries1 day ago

Betty Jean Menefee (1937 – 2026)

National News1 day ago

Trump Administration Appeals Judge’s Order Blocking White House Ban of 3 News Outlets

Local Government1 day ago

Town Council Discusses a Potential Joint Town-County Tourism MOU in Advance of Liaison Meeting

State News1 day ago

Loudoun Superintendent Pushes Back After Virginia Delegate Slams LGBTQ+ History Acknowledgment

State News1 day ago

Chesapeake Bay Gets a C+ in Overall Health, Virginia and Maryland Leaders Say Work to Protect It Must Continue

Meet the Candidates2 days ago

Allen Neel Says Front Royal Needs More Than Plans — It Needs Action

State News2 days ago

Warner Seeks a Final Term as Mizusawa Makes His Case for Change

Real Estate2 days ago

New Homes Stopped Shrinking. The Rooms Didn’t Stop Changing

Local News2 days ago

Lord Fairfax Health District Urges Residents To Prepare For Respiratory Virus Season

Local News2 days ago

Blue Ridge Wildlife Center Patient of the Week: Ruddy Duck

Community Events2 days ago

This Week’s Showtimes at Royal Cinemas as of October 15th

Arrest Logs2 days ago

POLICE: 7 Day FRPD Arrest Report 10/12/2026

Crime/Court2 days ago

Trial Date of January 6, 2027, Set in Misdemeanor Assault & Battery Case Against Hugh Henry

State News2 days ago

Virginia AG Launches Voter Protection Unit Ahead of Midterm Elections