I-66 Outside the Beltway Project: Lane Closures and Traffic Changes Week of September 8, 2019

Published

on

Lane restriping will occur on eastbound and westbound I-66 between I-495 and Route 29 in Gainesville from Sunday, September 8, through Saturday, September 14, from 9:30 p.m. to 5 a.m. with rolling multi-lane closures.

Transform 66 Outside the Beltway Project construction continues throughout the corridor during daytime and overnight hours as weather conditions allow. Current activities include:

• Lifting of bridge beam at the I-66/Route 28 Interchange
• Constructing bridge foundations at I-495, Route 28, Route 123, and Route 234 Business interchanges
• Constructing retaining walls along I-66 and Route 28
• Demolishing structures
• Small charge dynamite operations along I-66 in Prince William County
• Clearing trees and brush, grading, and installing drainage throughout the corridor
• Demolishing closed ramps at Route 123 Interchange
• Bridge work for new Bull Run Drive overpass
• Bridge work for the new I-66 West collector-distributor road over Route 234 Business (Sudley Road)
• Continued work at the future park and ride lots at University Boulevard (Gainesville) and Balls Ford Road (Manassas)
• Continued work on the new E.C. Lawrence Park Access Road
• Relocating underground and overhead utilities along I-66 and Route 28
• Corridor-wide roadway maintenance as needed

The Transform 66 Outside the Beltway project will add express lanes stretching 22.5 miles from the Capital Beltway to Route 29 in Gainesville, rebuild major interchanges along the I-66 corridor, create thousands of new park and ride spaces, and expand trail options for cyclists and pedestrians. Learn more at Transform66.org.

 

Upcoming Lane Closures and Traffic Changes
The following planned lane closures are expected to have significant traffic impacts. All work is subject to change based on weather and schedule. Find the latest information on travel conditions and work zones by visiting 511virginia.org or downloading the Virginia511 app.

ROUTE 29 / GAINESVILLE
I-66 East and West from Route 29 Gainesville to Route 234 Business (Prince William Parkway)
Monday, September 9, and Tuesday, September 10: 11 a.m. to noon
Temporary 15-minute stoppages of traffic for blasting operations on I-66 East and West between University Boulevard and Route 234 (Prince William Parkway). Stoppages will also occur on northbound Route 234 (Prince William Parkway) just north of the ramp to I-66 East, and on the ramp from Route 29 in Gainesville to I-66 East.

ROUTE 234 BUSINESS (SUDLEY ROAD) / MANASSAS
No significant traffic impacts scheduled.

ROUTE 28 (SULLY ROAD) / CENTREVILLE
Route 29 North and South from Machen Road to Stone Road
Monday, September 9: 9 p.m. to 5 a.m.
The left lane will be closed both northbound and southbound on Route 29 for crews to set up a safe work zone in the center median to build a temporary left turn lane from Route 29 South to I-66 West. The southern half of the left turn lane from Route 29 North to I-66 East will remain closed while the temporary ramp from southbound Route 29 to I-66 West is being built. Drivers should expect occasional 20-minute stoppages and slowdowns along northbound and southbound Route 29.

Ramp from Route 29 North to I-66 East
The previously announced one-month closure of the ramp from Route 29 North to I-66 East that was to begin on September 9 has been rescheduled to late 2019.

ROUTE 286 (FAIRFAX COUNTY PARKWAY)
No significant traffic impacts scheduled.

ROUTE 50 / FAIRFAX
No significant traffic impacts scheduled.

ROUTE 123 (CHAIN BRIDGE ROAD) / OAKTON – CITY OF FAIRFAX
No significant traffic impacts scheduled.

ROUTE 243 (NUTLEY STREET) / VIENNA
I-66 West from Gallows Road to Nutley Street
Wednesday, September 11: 9:30 p.m. to 5 a.m.
Three lanes will be closed on I-66 West for crews to shift traffic on I-66 near Vaden Drive. Drivers should expect occasional 20-minute stoppages and slowdowns along westbound I-66 and on the ramp from Virginia Center Boulevard to I-66 West.

I-495 (CAPITAL BELTWAY)
I-66 West from I-495 to Gallows Road
Ramp from I-495 North Express Lanes to I-66 West
Sunday, September 8, through Friday, September 13: 9 p.m. to 5 a.m.
Two left lanes will be closed on I-66 West for new Gallows Road bridge construction in center median. The ramp from the northbound I-495 Express Lanes to westbound I-66 will be closed nightly. Northbound I-495 Express Lanes North will be detoured to I-66 East to Route 7 (Leesburg Pike) West, make a left at the traffic signal, then stay to the right and follow signs to I-66 West.

Ramp from I-495 North Express Lanes to I-66 East
Saturday, September 14, Midnight to 4 a.m.
The ramp from the northbound I-495 Express Lanes to eastbound I-66 will be closed. Traffic will be detoured to I-66 West to Nutley Street South, stay to the right and follow signs to I-66 East.

Front Royal, VA
73°
Cloudy
5:53 am8:41 pm EDT
Feels like: 73°F
Wind: 1mph NE
Humidity: 95%
Pressure: 29.97"Hg
UV index: 1
TueWedThu
81°F / 68°F
81°F / 70°F
86°F / 70°F
State News19 minutes ago

Affordability, Jobs, Election Integrity Take Center Stage in Virginia’s 7th Congressional District Race

State News26 minutes ago

State Budget Extends Virginia Higher Education Displacement Commission Funding for Two Years

National News37 minutes ago

PJM Gets Green Light to Push Data Centers Onto Back-Up Power During Heat Wave

National News48 minutes ago

America’s 250th Birthday Celebrated, Despite Extreme Heat, Canceled Events

Interesting Things to Know3 hours ago

Ocean Ships at the Front Door

Interesting Things to Know3 hours ago

Solving the Lens Fogging Problem

Interesting Things to Know3 hours ago

How a King Became 42,000 Bullets

Local News21 hours ago

Storm Damage Closes Water Street in Front Royal

State News1 day ago

Relay for America Passes Through Leesburg Carrying Message of Unity Ahead of America 250

Food1 day ago

The Slab Pie: Apple Pie Built for a Picnic

Interesting Things to Know1 day ago

Can You Fund Retirement Without Stocks?

Historically Speaking2 days ago

‘From the Consent of the Governed’

Livestream - FR Cardinals2 days ago

Cardinals Host Strasburg Express Sunday, July 5 at Bing Crosby Stadium

Obituaries2 days ago

Minnie Cassandra Stribling McDaniel (1956 – 2026)

Interesting Things to Know2 days ago

The Signer Who Paid the Price

Agriculture2 days ago

Right Trees Can Make Windbreaks Stronger and Longer Lasting

Local News3 days ago

The Declaration of Independence at 250

Common Ground with Coolidge3 days ago

Coolidge’s 1926 Warning Still Echoes Nearly a Century Later

Local News3 days ago

VDOT: Warren County Traffic Alert for July 6 – 10 2026

Business Growth Series3 days ago

Business Growth Series: If You’re Not Creating Opportunities, You’re Losing Them

State News3 days ago

Virginia Launches Nation’s First Court-Ordered Speed Limiter Program for Reckless Drivers

State News3 days ago

Virginia’s Reproductive Rights Amendment Faces Legal Challenges Over Procedural Step, Language

State News3 days ago

Cities, Towns in Virginia and Across the Nation Revive Teen Curfews Amid Summer Crowds

State News3 days ago

Tick Bites Are Surging in the US This Year. Here’s What To Know.

Jefferson Forum3 days ago

Three Founders – One Day – One Destiny