Local Government
Boyers updates Town Council on infrastructure projects
Robbie Boyer, Public Works Director, updated Front Royal Town Council at its regular meeting on July 25, 2022.
Here’s the list of the current projects and their status:
- Curb & Gutter Installation Project – Installing 9,000’ of CG6 curb & gutter and CG9 driveway aprons on ten streets, the project is 50% completed and should be wrapped up by mid-September 2022.
- West Duck St Drainage Project – GEI started on July 18th, upgrading the existing 18” culvert to 30”, they’ll be finishing up the curb & gutter and backfilling this week and should be done by Thursday, July 28th.
- North Royal Ave Paving Project – Kick’in Asphalt started on North Royal Ave on July 18th. The milling and paving should be wrapped up with this on Friday, July 29th. Their line painters will be here on Sunday night and Monday night to install the new line markings. Then West 13th Street, George Banks and Belmont Avenue.
- 610B and 612 West 11th Street Storm Drain Upgrade – The town has installed the new 36” culvert between the two townhouses to the back of the property shy of the EDA fence. We received the signed right-of-entry agreement from the EDA this past Friday, July 22nd.
- Braxton Road and Manassas Avenue Waterline Upgrade Projects – We had a pre-bid meeting on June 27th at the town hall and had a good turnout of contractors show up. The bid opening is this Thursday at 2:00 pm. The plan is to have it ready for Town Council approval in August.
- John Marshall Hwy Waterline Upgrade Project – Bid will be posted on Friday, July 29th, with a pre-bid meeting on Thursday, August 11th, and bids will be opened on Tuesday, August 30th.
- Robinhood Lane Prv Vault – Order on April 26, 2022, and still looking at another ten weeks for delivery due to the traffic bearing hatch.
- Richmond Rd Prv Vault – Working on the vault drawings and bid documents, plan to bid out in late August 2022.
- Redundant Water-line Project – The pre-bid meeting was held on July 19th with 12 different contractors. The bid opening will be on August 24, 2022.
- Custom Storm Drain Lids -We’re in the process of coating the 25 custom storm drain lids for East Main Street. We’re planning to have them all coated by the end of next week.