I-66 Outside the Beltway Project: Lane closures and traffic changes Week of May 26, 2019
There will be no lane closures from noon on Friday, May 24, through noon on Tuesday, May 28, for the Memorial Day weekend.
As weather conditions allow, crews will continue corridor-wide roadway maintenance and address issues as needed, with daily multi-lane closures during daytime and overnight hours on I-66 East and West. Additional activities include:
• Constructing bridge foundations at I-495, Route 28, and Route 234 Business interchanges and Bull Run Drive overpass
• Constructing retaining walls along I-66 and Route 28
• Demolishing structures
• Blasting operations at the Route 28 interchange
• Clearing trees and brush, grading, and installing drainage throughout the corridor
• Demolishing closed ramps at Route 123 interchange
• Grading and installing drainage at the future Manassas/Balls Ford Road and Gainesville/University Boulevard park and ride lots
• Grading and excavating for the new E.C. Lawrence Park Access Road and temporary realignment of Braddock Road
• Relocating underground and overhead utilities along I-66 and Route 28

The Transform 66 Outside the Beltway project will add express lanes stretching 22.5 miles from the Capital Beltway to Route 29 in Gainesville, rebuild major interchanges along the I-66 corridor, create thousands of new park and ride spaces, and expand trail options for cyclists and pedestrians. Learn more at Transform66.org.
Upcoming Lane Closures and Traffic Changes
The following planned lane closures are expected to have significant traffic impacts. All work is subject to change based on weather and schedule. Find the latest information on travel conditions and work zones by visiting 511virginia.org or downloading the Virginia511 app.
ROUTE 29 / GAINESVILLE
No significant traffic impacts scheduled.
ROUTE 234 BUSINESS (SUDLEY ROAD) / MANASSAS
No significant traffic impacts scheduled.
ROUTE 28 (SULLY ROAD) / CENTREVILLE
Route 28 South at Braddock Road
Ramp from Route 28 North to I-66 East
Ramps from I-66 East and West to Route 28 North
Wednesday, May 29, through Friday, May 31: 11 a.m. to noon
Temporary stoppages of up to 15 minutes between 11 a.m. and noon for small charge blasting at the Route 28 interchange.
ROUTE 286 (FAIRFAX COUNTY PARKWAY)
No significant traffic impacts scheduled.
ROUTE 50 / FAIRFAX
I-66 East from Monument Drive to Jermantown Road
Friday, May 31, and Saturday, June 1: 9 p.m. to 9 a.m.
Three lanes will be closed to implement long-term lane shifts for construction. Drivers should expect occasional 20-minute stoppages and slowdowns along eastbound I-66.
ROUTE 123 (CHAIN BRIDGE ROAD) / OAKTON – CITY OF FAIRFAX
Ramp from Route 123 South to I-66 East
Tuesday, May 28, through Thursday, May 30: Midnight to 4 a.m.
The ramp from southbound Route 123 to eastbound I-66 will be closed between midnight and 4 a.m. Drivers will be detoured to I-66 West, follow signs to Route 50 East, then take the left exit to I-66 East.
Ramp from I-66 East to Route 123 South
Friday, May 31: Midnight to 4 a.m.
The ramp from eastbound I-66 to southbound Route 123 will be closed between midnight and 4 a.m. Drivers will be detoured farther east to Route 243 (Nutley Street) North, stay to the right and follow signs to I-66 West, then take the exit for Route 123 South.
ROUTE 243 (NUTLEY STREET) / VIENNA
No significant traffic impacts scheduled.
I-495 (CAPITAL BELTWAY)
No significant traffic impacts scheduled.
Commuter Alternatives
VDOT and the project team have invested in a broad range of programs to help commuters and others stay mobile and safe during construction. Learn more about carpool, vanpool, telework, and commuter bus alternatives.