There are no planned lane closures from noon on Wednesday, Nov. 21, through noon on Monday, Nov. 26, due to the Thanksgiving holiday. Have a Happy Thanksgiving!
Crews will continue shifting travel lanes and setting concrete barriers to create safe work zones along Interstate 66. Other upcoming planned construction activities include:
• *NEW* Constructing bridge abutment at Route 28 Interchange
• Ongoing lane striping and pothole repair work
• Constructing box culverts inside the Route 123 Interchange for shared use path
• Excavating and constructing retaining walls near Jermantown Road
• Grading, excavating, and clearing trees and brush at the Route 28, Route 123, Route 50, and I-495 interchanges and other work zone locations along the corridor
• Grading, excavating, and small charge blasting for storm drain trenches at the future University Boulevard Park and Ride Lot
• Grading and excavating for the new E.C. Lawrence Park Access Road
• Relocating underground and overhead utilities along I-66 and Route 28

The Transform 66 Outside the Beltway project will add express lanes stretching 22.5 miles from the Capital Beltway to Route 29 in Gainesville, rebuild major interchanges along the I-66 corridor, create thousands of new park and ride spaces, and expand trail options for cyclists and pedestrians. Learn more at Transform66.org.
Upcoming Lane Closures and Traffic Changes
The following planned lane closures are expected to have significant traffic impacts. All work is subject to change based on weather and schedule. Find the latest information on travel conditions and work zones by visiting 511virginia.org or downloading the Virginia511 app.
ROUTE 29 / GAINESVILLE
I-66 East from Route 29 in Gainesville to Route 28 (Sully Road) in Centreville
Saturday, November 17: 7 a.m. to 11 a.m.
Monday, November 19, and Tuesday, November 20: 10 a.m. to 4 p.m.
Multi-lane closures are planned as crews repair potholes between Route 29 in Gainesville and Route 28 (Sully Road) in Centreville.
ROUTE 234 (SUDLEY ROAD) / MANASSAS
I-66 West from Bull Run to Route 234 Business (Sudley Road)
Sunday, November 18: 8 p.m. to 5 a.m.
Three lanes will be closed to implement long-term lane shifts for construction. Additionally, the ramps from I-66 West to Route 234 Business (Sudley Road) and from Route 234 Business (Sudley Road) to I-66 West will be narrowed. Drivers should expect occasional 20-minute stoppages along westbound I-66.
ROUTE 28 (SULLY ROAD) / CENTREVILLE
I-66 East from Route 28 (Sully Road) to Route 286 (Fairfax County Parkway)
Sunday, November 18: 8 p.m. to 5 a.m.
Three lanes will be closed for construction activities. Drivers should expect occasional 20-minute stoppages.
Route 28 (Sully Road) North from Old Centreville Road to I-66
Sunday, November 18: 10 p.m. to 5 a.m.
Two right lanes will be closed for work on the traffic signal at the ramp to I-66 East. Drivers should expect intermittent 20-minute stoppages along northbound Route 28 (Sully Road). Additionally, drivers should expect occasional 20-minute stoppages on southbound Route 28.
I-66 West from Route 28 (Sully Road) in Centreville to Route 29 in Gainesville
Saturday, November 17: 7 a.m. to 11 a.m.
Monday, November 19, and Tuesday, November 20: 8 a.m. to 2 p.m.
Multi-lane closures are planned as crews repair potholes between Route 28 (Sully Road) in Centreville and Route 29 in Gainesville.
ROUTE 286 (FAIRFAX COUNTY PARKWAY)
I-66 East from Route 28 (Sully Road) to Route 286 (Fairfax County Parkway)
Sunday, November 18: 8 p.m. to 5 a.m.
Three lanes will be closed for construction activities. Drivers should expect occasional 20-minute stoppages and slowdowns.
ROUTE 50 / FAIRFAX
I-66 West from Chain Bridge Road (Route 123) to Route 50
Monday, November 19, and Tuesday, November 20: 9:30 p.m. to 5 a.m.
Three lanes will be closed to implement long-term lane shifts for construction. Drivers should expect occasional 20-minute stoppages.
ROUTE 123 (CHAIN BRIDGE ROAD) / OAKTON – CITY OF FAIRFAX
I-66 West from Chain Bridge Road (Route 123) to Route 50
Monday, November 19, and Tuesday, November 20: 9:30 p.m. to 5 a.m.
Three lanes will be closed to implement long-term lane shifts for construction. Drivers should expect occasional 20-minute stoppages.
ROUTE 243 (NUTLEY STREET) / VIENNA
No significant traffic impacts scheduled.
I-495 (CAPITAL BELTWAY)
No significant traffic impacts scheduled.