The Warren County Board of Supervisors met for a work session on February 23, 2021, to review and discuss ongoing work by county departments to forecast funding needs and scheduled projects in the offing in an uncertain funding climate. Newly appointed Fire Chief James Bonzano and Fire Marshal Gerry Maiatico provided the supervisors with a FEMA grant program the department has been using called Staffing for Adequate Fire and Emergency Response, or SAFER. According to FEMA, SAFER grants fund fire departments and volunteer firefighter interest organizations directly to help them increase capacity in their communities. The 2020 request will close March 12 and will require the Supervisors to decide before then how to allocate between $965,000 and nearly $2 million among the fire stations should the grant at the maximum level be approved. The 2020-21 budget for the entire Fire & rescue department is $3.1 million.

County Fire Chief James Bonzano, left, makes a point about Grant-funded staffing for Fire Stations in an era of increasing demand.
Ed Carter of VDOT provided an update of the Happy Creek Phase IV improvement project that was originally planned to require a road closure from June 14 to July 30 to coincide with school summer break. He explained that this project is intended to improve the roadway by eliminating some curves, hills, and blind spots.
The project has already been bid, and the bid was substantially lower than originally estimated, based on the projected closure of Happy Creek Road, giving the contractor unobstructed access to the site without having to maintain public access to the road during construction, which is planned to be completed in December.
The road closure will extend from Leach Run Parkway to Dismal Hollow Road. The reason for the possible extension is that since the project requires temporary relocation of utility lines and the Norfolk Southern Railroad must issue permits for that to happen on their right-of-way, Rural Electric Cooperative and Comcast must submit requests for the permits.
The permits were not requested as soon as they should have been, and it may not be possible to have those permits in hand prior to the scheduled construction start. In that event, Mr. Carter indicated that there may be a necessity for a two-week extension of the temporary closure. VDOT and the Town will coordinate with the school district to develop a plan if the extension of the road closure becomes necessary. Access to both Shenandoah Shores Road and Loop Road will be continued during the closure, and provision will be made for emergency vehicles.

Board of Supervisors Chair Cheryl Cullers reviews Project documents for the Happy Creek Improvement Phase 4 as the VDOT representative Ed Carter explains the potential for a delay in reopening Happy Creek Road after the current improvement project.
The School District representative, Aaron Mitchell, indicated it was a challenge to plan a reroute to accommodate the closure, then revert to a normal route within two weeks. It would be particularly hard on parents.
The closure extension may not be necessary, but if it is not possible to work out a plan for the closure, Mr. Carter indicated that the project could be pushed to next year.
VDOT will undertake to have a discussion with the school superintendent this week.
Residents of Happy Creek Road will be vitally interested in progress towards a solution as the start of this improvement project nears.