Transform 66 Outside the Beltway Project construction continues throughout the corridor during daytime and overnight hours as weather conditions allow. Current activities include (new or updated items are bolded):

• The ramp from I-66 East to Route 123 North is scheduled to close Friday night, Feb. 21. Drivers will exit toward Route 123 South, stay left, then use two signal-controlled turn lanes to turn left onto northbound Route 123. Learn more

• Bridge demolition at Route 123 (Chain Bridge Road) and Fairfax County Parkway Route (Route 286)

• Constructing bridge foundations at Route 29, Route 28, Waples Mill Road, Jermantown Road, Route 123, Vaden Drive, and I-495

• Small charge dynamite operations along I-66 East and West near Route 28

• Bridge deck work for new collector-distributor road over Route 234 Business (Sudley Road), new Route 28 bridges over I-66, and new Poplar Tree Road bridge over Route 28

• Relocating water lines at Jermantown Road, Stringfellow Road, and Gallows Road

• Constructing new utility duct bank and relocating underground utilities along I-66 East

• Constructing retaining walls along I-66 and Route 28

• Corridor-wide roadway maintenance as needed

The Transform 66 Outside the Beltway project will add express lanes stretching 22.5 miles from the Capital Beltway to Route 29 in Gainesville, rebuild major interchanges along the I-66 corridor, create thousands of new park and ride spaces, and expand trail options for cyclists and pedestrians. Learn more at Transform66.org.

 

Upcoming Lane Closures and Traffic Changes
The following planned lane closures are expected to have significant traffic impacts. All work is subject to change based on weather and schedule. Find the latest information on travel conditions and work zones by visiting 511virginia.org or downloading the Virginia511 app.

ROUTE 29 / GAINESVILLE
No significant traffic impacts scheduled.

ROUTE 234 BUSINESS (SUDLEY ROAD) / MANASSAS
Ramp from I-66 West to Route 234 Business (Sudley Road) North
Tuesday, Feb. 18: Midnight to 4 a.m.
The ramp will be closed for underground drainage culvert work. Traffic will be detoured to Route 234 Business South, turn right at the third traffic signal onto Coverstone Drive, take the first right at Miramar Drive, turn right on Balls Ford Road, then turn left at the traffic signal on to northbound Route 234 Business.

I-66 East from Route 234 Business (Sudley Road) to Route 29 Centreville
Wednesday, Feb. 19: 9 p.m. to 5 a.m.
Three left lanes will be closed for overhead gantry removal. Drivers should expect occasional 20-minute stoppages between midnight and 4 a.m.

Compton Road at I-66
Tuesday, Feb. 18, through Friday, Feb. 21: 10 p.m. to 5 a.m.
Compton Road will be closed under I-66 while crews install bridge beams over Compton Road. Traffic will be directed to Route 29 (Lee Highway) via Bull Run Post Office Road or Old Centreville Road as an alternate and then back to Compton Road. Learn more

ROUTE 28 (SULLY ROAD) / CENTREVILLE
Route 28 North and South between Route 29 and Braddock Road
Braddock Road at Route 28
Ramp from Route 28 North to I-66 East
Wednesday, Feb. 19, through Friday, Feb. 21: 11 a.m. to noon
Temporary 15-minute stoppages of traffic on Route 28 North and South, and on Braddock Road near Route 28 for blasting operations. Additionally, stoppages will occur on the ramps from Route 28 North to I-66 East and West.

Compton Road at I-66
Tuesday, Feb. 18, through Friday, Feb. 21: 10 p.m. to 5 a.m.
Compton Road will be closed under I-66 while crews install bridge beams over Compton Road. Traffic will be directed to Route 29 (Lee Highway) via Bull Run Post Office Road or Old Centreville Road as an alternate and then back to Compton Road. Learn more

I-66 East from Route 234 Business (Sudley Road) to Route 29 Centreville
Wednesday, Feb. 19: 9 p.m. to 5 a.m.
Three left lanes will be closed for overhead gantry removal. Drivers should expect occasional 20-minute stoppages between midnight and 4 a.m.

ROUTE 286 (FAIRFAX COUNTY PARKWAY) / FAIR LAKES
Stringfellow Road between Fair Lakes Boulevard and Village Square Drive
Monday, Feb. 17, through Friday, Feb. 21: 9 p.m. to 3 p.m.
Friday, Feb. 21, from 9 p.m. until 3 p.m. Monday, Feb. 24
The right lane of southbound Stringfellow Road will be closed for underground utility relocation. The lane will be reopened weekdays between 3 p.m. and 9 p.m. to accommodate the evening rush.

Route 286 North from Route 29 (Lee Highway) to I-66
Monday, Feb. 17, through Thursday, Feb. 20: 9 p.m. to 5 a.m.
Two lanes will be closed for demolition of I-66 bridges over Route 286. Drivers should expect occasional 20-minute stoppages along northbound Route 286.

Route 286 South from Fair Lakes Parkway to I-66
Tuesday, Feb. 18, through Thursday, Feb. 20: 9 p.m. to 5 a.m.
Friday, Feb. 21: 10 p.m. to 8 a.m.
Two lanes will be closed for demolition of I-66 bridges over Route 286. Drivers should expect occasional 20-minute stoppages.

Ramp from I-66 West to Route 286 (Fairfax County Parkway) South
Thursday, Feb. 20, and Friday, Feb. 21: Midnight to 4 a.m.
The ramp will be closed for overhead bridge demolition. Traffic will be directed to Route 286 North, stay to the right and take the exit for Fair Lakes Parkway/Monument Drive, at the traffic signal make a left on to westbound Fair Lakes Parkway, then stay to the left and follow signs to Route 286 South.

ROUTE 50 / FAIRFAX
I-66 East from Route 608 (West Ox Road) to Route 123 (Chain Bridge Road)
Tuesday, Feb. 18: 9 p.m. to 5 a.m.
Three left lanes will be closed for overhead gantry removal. Drivers should expect occasional 20-minute stoppages between midnight and 4 a.m.

Ramp from Route 50 West to I-66 West
Tuesday, Feb. 18: Midnight to 4 a.m.
The ramp will be closed for utility work. Traffic will be detoured farther west to Route 608 (West Ox Road) South, stay to the right for Route 50 East, then follow signs to I-66 West.

ROUTE 123 (CHAIN BRIDGE ROAD) / OAKTON – CITY OF FAIRFAX
I-66 East from Waples Mill Road to Route 123 (Chain Bridge Road)
Tuesday, Feb. 18: 9 p.m. to 5 a.m.
Three lanes will be closed for overhead bridge demolition at Route 123 between 11 p.m. and 4 a.m.

I-66 East at Route 123 (Chain Bridge Road)
I-66 East Collector-Distributor Lane at Route 123 (Chain Bridge Road)
Ramps from I-66 East to Route 123 North and South
Wednesday, Feb. 19, and Thursday, Feb. 20: Midnight to 4 a.m.
Friday, Feb. 21, and Saturday, Feb. 22: Midnight to 5 a.m.
The ramps from I-66 East to Route 123 North and South and the collector-distributor lane will be closed for overhead bridge demolition at Route 123. Traffic will be detoured farther east to Route 243 (Nutley Street) North, stay to the right for I-66 West, then follow signs to Route 123 North or South. Additionally, the right lane of I-66 East at Route 123 will be closed.

Route 123 (Chain Bridge Road) North and South from I-66 to Eaton Place
Friday, Feb. 21: 10 p.m. to 8 a.m.
One lane will be closed on northbound and southbound Route 123 for crews to implement a traffic pattern change at the ramp from I-66 East to Route 123 North.

ROUTE 243 (NUTLEY STREET) / VIENNA
No significant traffic impacts scheduled.

I-495 (CAPITAL BELTWAY) / DUNN LORING
Ramp from I-66 East to 495 Express Lanes South
Tuesday, Feb. 18: 9 p.m. to 5 a.m.
The ramp from I-66 East to the 495 Express Lanes South will be closed for utility work. Drivers will be directed to take the exit for the I-495 South general-purpose lanes.

Commuter Alternatives
VDOT and the project team have invested in a broad range of programs to help commuters and others stay mobile and safe during construction. Learn more about carpool, vanpool, telework, and commuter bus alternatives.

Community Events11 hours ago

Izaak Walton League’s Final Kid Saturday of 2026 Brings Holiday Crafts and Family Fun to Bentonville

Obituaries11 hours ago

Gary Brent Sullins (1959 – 2026)

Obituaries11 hours ago

Kenneth Leroy “Kenny” Corbin (1962 – 2026)

Community Events11 hours ago

Front Royal Honors Veterans with a Message of Sacrifice, Unity, and Love of Country

State News16 hours ago

Spanberger, Virginia Democrats Pitch Medical Debt Relief, Data Center Limits for 2027

State News16 hours ago

Gun Violence Prevention Programs Saved Virginia Hospitals More than $100 Million

Local Government19 hours ago

Warren County Supervisors Ramp Up Search for a Permanent County Administrator Replacement

Uncategorized19 hours ago

Gun Violence Prevention Programs Saved Virginia Hospitals More Than $100 Million

Opinion19 hours ago

Commentary: This Veterans Day, Give Veterans More Than Thanks

National News19 hours ago

Winter Is Coming. Can Democrats Succeed in Chilling Soaring Energy Prices?

National News19 hours ago

Defense Secretary Hegseth Calls Impeachment Push a ‘Farce’ as US House Heads Toward Vote

State News19 hours ago

Three Roadside Workers Killed in Virginia as Officials Urge Drivers to Slow Down and Move Over

Interesting Things to Know21 hours ago

A New Reason to Take Your Phone on the Dog Walk: Discover the Birds Singing Around You

Health22 hours ago

A Cancer Vaccine Made for One Patient at a Time Shows Promise Against Melanoma

Local News1 day ago

Blue Ridge Wildlife Center Patient of the Week: Canada Goose

arrest logo
Arrest Logs1 day ago

POLICE: 7 Day FRPD Arrest Report 11/9/2026

Community Events1 day ago

This Week’s Showtimes at Royal Cinemas as of November 12th

Local Government1 day ago

Town Council Arrives at Consensus on Joint Tourism Agreement with the County

Local News1 day ago

From Steel to Sharp: Front Royal Craftsman Turns Handmade Knives Into Works of Art

Food2 days ago

Jest a Moment: Great Unheralded Moments in Food History

State News2 days ago

Virginia Elected a Woman Governor. The State Constitution Still Says ‘He’

State News2 days ago

JLARC: Data Center Tax Break Accounts for 60% of Virginia’s Incentive Spending

Opinion2 days ago

Commentary: The Blue Tsunami Has a Message for Virginia Democrats on Data Centers and Campaign Finance

National News2 days ago

Trump Open to Immigration Deal, Calls Crackdown ‘Too Tough,’ Despite Miller Promotion

Interesting Things to Know2 days ago

That Flashing Orange Hand Doesn’t Mean Run: What Pedestrian Signals Really Mean