Virginia Has a New Two-Year Budget. Here’s What Lawmakers Now Require of Data Centers

Published

on

A new tax has been activated for data centers, the most energy-intensive industry in Virginia, through a provision of the two-year state budget that the legislature finalized Monday.

Marvell data center in Culpeper County. The Virginia legislature’s new two-year budget imposes new standards on the industry to address concerns about data centers’ energy use and environmental impacts. (Photo by Evan Visconti/Virginia Mercury)

Virginia General Assembly approves Spanberger’s budget amendments, ending monthslong impasse

The spending plan preserves data centers’ sales and use tax exemption, the focus of a protracted legislative fight over the past few months. But the new tax represents the state’s first major efforts to claw back millions from the industry specifically for their energy use and address residents’ concerns about the rapidly multiplying facilities.

“We have more data centers than anywhere else in the entire world, and I think the entire country is looking to us to set policy on this, and we’ve taken the first step this year, in terms of generating some more revenue,” said Sen. Scott Surovell, D-Fairfax.

Energy consumption tax

Data centers will now have to pay a $.011 tax on every kilowatt hour of power they use. The state can collect a maximum of  $600 million a year, a total of $1.2 billion to be collected over the biennium.

Any amount collected over the cap will be refunded to data centers at the end of each fiscal year.

According to the 2024 Joint Legislative Audit and Review Commission report on data centers, the industry used approximately 5,050 megawatts of power that year, based on peak load forecasts by Dominion Energy and Mecklenburg, Northern Virginia, and Rappahannock electric cooperatives in August of 2023.

Dominion reported at the end of 2025 that they had 70,000 MW of large load energy requests in their queue.

The state sales and use tax exemption saves data centers an estimated $1.9 billion a year, a figure that dwarfs the expected revenue from the new energy consumption tax.

A work group will study how the tax exemption could be phased out or other ways to make data centers pay their fair share, a position Senate Finance Chair Sen. L. Louise Lucas, D-Portsmouth, and other lawmakers have pushed for months.

The work group will present a report to the General Assembly in November to help lawmakers craft bills for the January legislative session. Lucas has stressed that the discussions around the sales tax exemption are not over.

Water scarcity areas

Data centers will now be required to try to limit their water use, another new provision of the budget.

Data centers that do not use closed-loop cooling systems use millions of gallons of water a year. The Department of Environmental Quality will locate cooling water scarcity areas, where using drinkable water to cool down the computers could put local water quality and availability at risk.

Those scarcity areas must be identified by July 2027. Before 2032, data centers located in scarcity areas or in the Eastern Virginia Groundwater Management Area, which covers all areas east of I-95, must show they’ve minimized the use of any water for cooling purposes.

They will be required to use the best available water-efficient technologies  — like air cooling, closed-loop systems, recycled water, stormwater reuse, non-potable reclaimed water use —  or other department-approved methods.

Gov. Abigail Spanberger proposed an amendment to the data center water use measure on  Friday, altering the language to make data centers show they have used less water for cooling in order to use evaporative cooling, in part, with other DEQ-approved methods.

The previous version of the budget passed by the House and Senate last week did not allow for evaporative cooling at all in the scarcity areas.

Some lawmakers felt the governor’s tweaks were too subjective and left the door open for data centers to continue using evaporative cooling.

Sen. Danica Roem, D-Prince William, stated that the language Spanberger pitched, saying data centers “shall demonstrate to the satisfaction of the department that it has minimized the use of any type of water for cooling purposes,” is not clear enough and does not lay out specific limits for water use.

“My concern here always goes back to sufficient legal recourse because right now, we have plans and we’ve got minimalization, but what we don’t have, in my point of view, is sufficient requirements,” Roem said on Monday at the Capitol.

Data centers in those areas will only be able to use direct evaporative cooling in conjunction with one of the other technologies. But while the closed-loop systems use less water, they use more energy than the non-closed-loop systems.

Budget conferee Sen. Richard Stuart, R-King George, said that allowing evaporative cooling at all is not a way to conserve water, even if it is in conjunction with the more water-efficient methods. The senator pushed his colleagues to reject the amendment, but it ultimately passed.

“If you’re gonna evaporate 50% of the water into the atmosphere, how will we be conservative with water?” Stuart asked. “This was one of the most significant conservation measures that we got in the conference report. We couldn’t get anything on electricity … we got promises to do something in the future. And now they want to take this away from us.”

The Department of Environmental Quality will be required to conduct a study by Oct. 15 of this year on how to retrofit existing data centers in the groundwater management area to use air cooling, 100% recycled water/stormwater, or switch to a closed loop system.

Noise levels

The new budget also mandates DEQ to regulate data centers’ noise levels for the first time.

By 2029, the department will have to find exactly how quiet a data center could be and make that the standard for the industry, starting in 2030. Noise produced by the warehouse-like facilities has been a rising concern for people who live in areas where data centers have been proposed.

After those regulations are put in place, a facility in violation of the noise ordinance will face a fine of $32,500 a day.

 

by Shannon Heckt, Virginia Mercury


Virginia Mercury is part of States Newsroom, a nonprofit news network supported by grants and a coalition of donors as a 501c(3) public charity. Virginia Mercury maintains editorial independence. Contact Editor Samantha Willis for questions: info@virginiamercury.com.

Front Royal, VA
70°
Showers in the Vicinity
6:05 am8:33 pm EDT
Feels like: 70°F
Wind: 5mph SSW
Humidity: 96%
Pressure: 29.72"Hg
UV index: 0
ThuFriSat
81°F / 55°F
82°F / 63°F
81°F / 66°F
Local News11 hours ago

Blue Ridge Wildlife Center Patient of the Week: American Barn Owl

State News12 hours ago

After Taking Off in Charlottesville, Feds Plan National Electric Aircraft Charging Network Rollout

report logo
Arrest Logs12 hours ago

POLICE: 7 Day FRPD Arrest Report 7/20/2026

National News12 hours ago

FDA: Taylor Farms iceberg lettuce sample produced a false positive for cyclospora

State News12 hours ago

Data Centers Want to Build Their Own Gas Turbines. Would That Skirt State Renewable Energy Laws?

Legal Notices12 hours ago

Legal Notice: Virginia Alcoholic Beverage Control (ABC) Authority

Historically Speaking16 hours ago

Removing a Senator

Opinion17 hours ago

The Dillon Rule Doesn’t Say What Mr. Cuddeback Implies

Health21 hours ago

Test Your Balance Before the Job Tests It for You

Legal Notices1 day ago

Legal Notice: Virginia Alcoholic Beverage Control (ABC) Authority

State News2 days ago

Late On Rent? New Virginia Law Gives Tenants More Time and Protection From Eviction 

State News2 days ago

Virginia Schools Gain Spending Flexibility Under Federal Program

Travel2 days ago

Three Useful Car Gadgets for a Better Summer Road Trip

Mature Living2 days ago

When He Retires, Who Runs the Kitchen?

Interesting Things to Know3 days ago

State of the Assistants: The Second Great Voice-Assistant War

Local News3 days ago

Front Royal Family Practice Files $5-Million Civil Claim Against Valley Health and Warren Memorial Hospital

Local News3 days ago

Virginia Violent Crime Fell Nearly 6% in 2025, State Police Report Shows

Crime/Court3 days ago

Virginia State Police Seize More Than $3.3 Million in Drugs During Weekly Operations

EDA in Focus3 days ago

30-Acre ITFederal Property at Avtex Scheduled for Auction to Help Resolve EDA ‘Financial Scandal’ Debt to First Bank & Trust

Crime/Court3 days ago

Grand Jury Returns Dozens of Indictments in Warren County

Local News3 days ago

VDOT: Warren County Traffic Alert for July 20 – 24, 2026

Local News4 days ago

Fauquier Health CEO Earns National Recognition for Second Straight Year

Local News4 days ago

Trail Option Draws Strongest Support in VDOT Shenandoah Rail Corridor Survey

Opinion4 days ago

A Path to Fiscal Responsibility and Public Wellness

Jefferson Forum4 days ago

Smoke Does Not Stop at the Border — Neither Does the Climate